Talk:QUESTIONNAIRE sprint 25-01-2010
Sprint 25-01-2009 - 10-02-2010
9 days : Fixing 14 bugs and 1 standard task
9.5 days VN2886QNR - SRM - Background information - Support more than one request from a site Coding: 4 Review: 0.5 Test : 2 fix bug : 2
4.25 VN2868QNR - Fix Close button in questionnaire viewer
- Write FD + Getting the request from client: 0.5d + Write the FD: 1d - Coding: 1.5 - Fixing review code: 0.25d - Fixing bug: 0.5d - Testing: 0.5d
Total : 22.75d