Sprint 25-01-2009 - 10-02-2010

9 days : Fixing 14 bugs and 1 standard task

9.5 days VN2886QNR - SRM - Background information - Support more than one request from a site Coding: 4 Review: 0.5 Test : 2 fix bug : 2


4.25 VN2868QNR - Fix Close button in questionnaire viewer

- Write FD
 + Getting the request from client: 0.5d
 + Write the FD: 1d
- Coding: 1.5
- Fixing review code: 0.25d
- Fixing bug: 0.5d
- Testing: 0.5d

Total : 22.75d