Talk:Core sprint 22-12-2008
Contents
Sprint for Core (13-01-2008 - 05-02-2009)
Goal
One thing at a time
Burndown Chart
Time capacity: 94
Estimated time budget: 58.5 (= 62.23%)
Expected velocity: 62.23
Sprint-backlog
VN2444COR - Image button control
Description | Due to the fact that we are refactoring common buttons, and these buttons share some common behaviors. Then a common super control will be created. |
---|---|
Main responsible | Nguyễn Thị Vân Anh, Phạm Ngọc Sơn |
Importance | |
Work days | 5.5 |
Status | To do |
Deadline |
VN2124COR - Add resource to favorites button control
Description | The add resource to favorite button control is a quite small control. It will have the following input parameters. 1.Enabled (whether the button is enabled or disabled) – default will be enabled 2.Add resource to favorites button text (the key used for specifying the mouse over text of this button) This design does not include all the existing Add resource to favorites buttons that need to convert into using this control. This design does also not include the design for the actual “add resource to favorites dialog” which is expected to be a separate control. |
---|---|
Main responsible | Nguyễn Thị Vân Anh, Phạm Ngọc Sơn |
Importance | |
Work days | 4 |
Status | To do |
Deadline |
VN2123COR - Open resource button control
Description | The Open resource button control is a quite small control. It will have the following input parameters.
1.Enabled (whether the button is enabled or disabled) – default will be enabled
|
---|---|
Main responsible | Nguyễn Thị Vân Anh, Phạm Ngọc Sơn |
Importance | |
Work days | 3.5 |
Status | To do |
Deadline |